Building Update



Week 15 Update

Front entrance

Started brick at front entrance

Fire wall at front gable

Starting window installation

Interior walls and social hall expansion

Southwest corner

Southeast corner


Week 14 Update

New front entrance

Front entrance

Front entrance framing

Windows are on site

Social hall addition

Southwest corner

Southeast corner


Week 13 Update

Front entrance

Existing corridor and furnace room

Corridor

Meeting room 1

Social hall expansion

Southwest corner

Southeast corner


Week 12 Update

Tie in to existing

TJI’s over meeting rooms

Tower

Trusses over social hall

Southwest corner

Southeast corner


Week 11 Update

Demo at electric room for new firewall

Demo at front entrance

Structural components

Southwest corner

Southeast corner


Week 10 Update

Interior Framing at Corridor

Interior Framing

CT Cabinet and Disconect

Transformer set

Old Transformer loc removed

Exterior Framing Back

Exterior Framing, Window Openings

Tower Exterior Framing


Week 9 Update

Southwest corner

Southeast corner

South steps and frost stoop

Ramp and steps at new entrance

Front entrance and new restroom

Electric room

New restroom floor poured



Week 8 Update

Social hall temporary partition

New front entrance and restroom

New underground plumbing backfilled

New electric service

Utilities

Southwest corner

Southeast corner



Week 7 Update

Southwest corner

Southeast corner

New electric service

New transformer location

Plumbing underground

Plumbing and electrical underground

Existing electrical room

Social hall temp. partition




Week 6 Update

Southeast corner

Southwest corner

Front entrance

New restroom

Electric room

Meeting room 5/6 area




Week 5 Update

Electric transformer and primary trench

Front entrance

Meeting room 5 area

Electric secondary trench

Southwest corner

Southeast corner




Week 4 Update

Lay down area

Safety at front entrance

Front entrance area

Existing furnace room

Meeting room 5 area

Northeast corner of addition

Southwest corner

Southeast corner




Week 3 Update

Equipment mobilization

Safety

Meeting room area

Entrance 121

Walkway removed

Northeast corner of addition

Southwest corner

Southeast corner




Ground Breaking

After many years of planning, we have only reached this moment because of you and your generosity. Watch Ground Breaking Video